Leisure Trail Work on Green Dolphin Way Underway Through End of April

This week, KICA will begin work to upgrade the leisure trail and transitions on the leisure trail adjacent to Green Dolphin Way and Turtle Point Lane. This work will be done in three stages, and is anticipated to be complete by the end of April.

Stage 1: Demolition and installation of flush curbing at each road transition. Following this stage, the curbing will cure before access to the trail is reopened.
Stage 2: Specific areas of the trail asphalt will be milled.
Stage 3: The entire trail will be paved with new asphalt.

During this work, there will be closures in the trail locations highlighted above. The length of closures will vary, depending on the work performed. For your safety, please obey all signage and do not enter a closed work zone.

This work is weather-dependent; dates may change as needed.