KIU Secondary Water Line Project Updates

May 5, 2016 – Clearing began May 4 on the KIU site on Governors Drive and the drill site on Marsh Island Drive. This work will be completed by May 8. No additional clearing on Kiawah Island will be done at this time.

Once the clearing is completed, the contractor will initiate the short directional drill from the Governors Drive site to the clearing on Governors Drive after Blue Heron. Drilling is expected to take approximately 14 days, including set-up. After completion, the contractor will begin moving his equipment onto the already cleared drill site on Marsh Island Drive.